MSG-3 Analysis, the MRB Report and FEC Codes 5 to 9: What CAMO Engineers Need to Know

George Spiteri
MSG-3 Analysis, the MRB Report and FEC Codes 5 to 9: What CAMO Engineers Need to Know

Every scheduled task in a large aircraft maintenance programme (AMP) has a history. Most of them were born in an MSG-3 working group, approved in a Maintenance Review Board (MRB) report and then republished by the type certificate holder in the maintenance planning document (MPD). The two-digit code beside an MRB systems task, its failure effect category (FEC), tells you why the task exists and how hard it will be to change.

This guide explains MSG-3 analysis, the MRB process and the meaning of FEC 5, 6, 7, 8 and 9, and then shows why those codes matter to a CAMO engineer who develops or amends an AMP under point M.A.302 of Regulation (EU) No 1321/2014.

 

Quick answers
  • MSG-3 is an industry decision logic, published by Airlines for America (A4A), used to develop the initial minimum scheduled maintenance of new aircraft and engines. It starts from the consequence of each failure rather than from the component.
  • The MRB report (MRBR) is the output of that analysis, produced by industry working groups and approved by the authority. EASA describes its content as initial minimum recommended scheduled maintenance and inspection requirements.
  • FEC codes are the five MSG-3 failure effect categories for systems and powerplant: 5 evident safety, 6 evident operational, 7 evident economic, 8 hidden safety and 9 hidden non-safety.
  • Why it matters: EASA FAQ 48248 treats FEC 5 and FEC 8 tasks as safety-related, so escalating their intervals needs direct approval by the competent authority.

What is MSG-3?

MSG stands for Maintenance Steering Group, a joint team of manufacturers, operators and authorities. The first MSG document appeared in 1968 for the first generation of wide-body airliners, MSG-2 followed in the early 1970s, and MSG-3 was first published in 1980. A4A publishes MSG-3 in two volumes: Volume 1 for fixed-wing aircraft and Volume 2 for rotorcraft. It is revised periodically, so always check which revision applied to the type you work on.

The step from MSG-2 to MSG-3 changed the question being asked. MSG-2 worked bottom-up, component by component, and used process labels such as hard time, on-condition and condition monitoring. MSG-3 works top-down: it starts with the functions of a system, asks what happens when each function fails, and only then selects a task. The consequence of the failure, not the part, drives the decision.

EASA recognises MSG-3 as an appropriate methodology for developing initial minimum scheduled maintenance. Its Certification Memorandum CM-MRB-001 expects the applicant to use the latest MSG-3 revision published at the date of the type certificate or supplemental type certificate application.

 

Who produces the MRB report?

The MRB process is a partnership with clearly separated roles. Industry does the analysis; the authority reviews and approves it

BodyRole in the MRB Process
Industry Steering Committee (ISC)Manufacturer and operator representatives who direct the work, agree the policy and procedures handbook (PPH) and submit the MRB report proposal.
Maintenance working groups (MWGs)Specialists from the manufacturer and operators who apply MSG-3 logic to systems, powerplant, structures, zones and L/HIRF. CM-MRB-001 aims for at least three operators at working group meetings.
Maintenance Review BoardThe authority team that reviews the analysis. At EASA, an MRB chairperson leads the team and recommends approval of the MRBR.
IMRBPBThe International Maintenance Review Board Policy Board. It publishes issue papers and the international MRB policy (IMPS), which feed later MSG-3 revisions.

Once approved, the MRBR becomes a source document for every operator of the type. CM-MRB-001 states that it is one of the sources used to develop or revise the operator's maintenance programme under Part-M, and that task intervals may be optimised only with satisfactory substantiation and authority approval, or under an approved reliability programme.

 

MRBR, MPD and AMP are three different documents

 

DocumentWhat it containsWho issues it
MRB reportInitial minimum scheduled maintenance from the MSG-3 analysis.Industry analysis, approved by EASA through the MRB process.
MPDMRBR tasks plus other sources such as certification maintenance requirements (CMRs), airworthiness limitations and manufacturer recommendations, with effectivity and planning data.The type certificate holder, as part of its instructions for continued airworthiness (21.A.7).
AMPAll maintenance to be carried out on the operator's aircraft, adapted to its configuration and operation.The owner or CAMO; approved directly by the competent authority or indirectly through the CAMO procedure (M.A.302).

A common audit finding starts with the belief that the MPD is the AMP. It is not. The AMP must comply with the instructions issued by design approval holders (M.A.302(d)), but it is the operator's own controlled document.

 

How MSG-3 analyses aircraft systems

For systems and powerplant, the working group first selects the maintenance significant items (MSIs): items whose failure could affect safety, could go undetected, or could have a significant operational or economic impact. For each MSI it lists the functions, the functional failures, the failure effects and the failure causes. Then it applies the decision logic in two levels.

 

Level 1: which failure effect category?

Level 1 is a short sequence of yes-or-no questions asked about each functional failure:

  1. Is the failure evident to the operating crew during the performance of their normal duties?
  2. If evident: does the failure, or secondary damage resulting from it, have a direct adverse effect on operating safety?
  3. If hidden: does the combination of the hidden failure and one additional failure have an adverse effect on operating safety?
  4. If evident and not safety-related: does the failure have a direct adverse effect on operating capability?

 

The answers place the failure in one of five categories, numbered 5 to 9.

 

Level 2: which task, if any?

Level 2 then works through the possible task types in a fixed order and keeps a task only if it is applicable (it suits the failure characteristics) and effective (it achieves the objective of the category). For safety categories, effective means reducing the risk of failure to an acceptable level. For the other categories, it means the task costs less than the failure it prevents.

 

FEC codes 5 to 9 and what they mean

FECCategoryMeaning(paraphrased from MSG-3)Task Rule
5Evident safetyThe failure, or its secondary damage, has a direct adverse effect on operating safety.A task is required. If no task or combination is effective, redesign is mandatory.
6Evident operationalThe failure affects operating capability, for example delays, cancellations or operating restrictions, but not safety.A task is desirable if it costs less than the operational loss plus repair.
7Evident economicThe failure has an economic effect only, mainly the cost of repair.A task is desirable if it costs less than the repair.
8Hidden safetyThe failure is not evident to the crew, and combined with one additional failure it has an adverse effect on operating safety.A task is required to assure the availability of the function. If none is effective, redesign is mandatory.
9Hidden non-safetyA hidden failure that, combined with one additional failure, has an economic or operational effect but no safety effect.A task is desirable if it is cost-effective.

 

Two things are worth noticing. First, the categories are about consequence, not likelihood: a reliable component can still be FEC 8 if its hidden failure would matter in combination with another failure. Second, FEC 8 tasks are often failure-finding tasks, such as operational checks of standby or protective functions that nobody uses in normal operation.

 

MSG-3 task types you will see in an MPD

 

MSG-3 TaskPurpose
Lubrication or servicingReplenish consumables to keep the inherent design capability.
Operational or visual checkFailure finding: confirm that an item fulfils its intended purpose. Selected for hidden functions only.
Inspection or functional checkDetect degradation: a general visual, detailed or special detailed inspection, or a quantitative functional check against limits.
RestorationReturn the item to a specific standard, from cleaning to overhaul.
DiscardRemove the item from service at a specified life limit.
CombinationTwo or more tasks together. Used only for safety categories.

Task abbreviations such as LU, SV, OPC, VCK, GVI, DET, SDI, FNC, RST and DIS are common, but each manufacturer defines its own in the MPD introduction. Read that introduction before reading the task list.

 

Structures, zonal, EWIS and L/HIRF analysis

MSG-3 does not use FEC codes outside systems and powerplant. Structure is analysed item by item: each structural significant item (SSI) is assessed for accidental damage, environmental deterioration (corrosion and the deterioration of non-metallic materials) and fatigue damage. The zonal analysis applies general visual inspections zone by zone. The enhanced zonal analysis procedure (EZAP), described for EASA in AMC 20-21, looks at electrical wiring interconnection systems (EWIS) and can add stand-alone wiring tasks where the risk is higher. The L/HIRF analysis keeps lightning and high-intensity radiated field protection effective.

This is why an MPD source column can read 'MRB' without any FEC. It is still an MRB task, and for escalation purposes EASA treats SSI, L/HIRF and stand-alone EWIS tasks as safety-related, just like FEC 5 and FEC 8.

 

MRB tasks are not airworthiness limitations

Certification maintenance requirements and airworthiness limitations come from certification, not from the MRB. CMRs are periodic tasks established during type certification to detect latent failures that would contribute to catastrophic or hazardous failure conditions (AMC 25.19). Airworthiness limitations, such as life limits and damage-tolerance inspections, sit in the Airworthiness Limitations Section, which is part of the type design (21.A.31(a)(3)). The MSG-3 analysis may produce the same task, but when a CMR or ALS code appears beside an MRB code, the mandatory code governs: the task cannot be escalated or varied through the AMP.

 

Why the FEC code matters to the CAMO

Once the aircraft is in service, the FEC code stops being an engineering label and becomes a routing instruction. EASA FAQ 48248 explains how AMP task intervals may be escalated. Where the type went through the MRB process, it lists as safety-related: FEC 5 and FEC 8 tasks for systems and powerplant, SSI tasks, L/HIRF tasks and stand-alone EWIS tasks from the EZAP.

 

Task being escalatedApproval Route under Part-M 9EASA FAQs 48248 and 19061)
ALS item (life limit, ALI, CMR)Not through the AMP. Escalation changes the type design and needs agreement between the design approval holder and EASA. Certain two-star CMRs may be adjusted under AMC 25.19.
FEC 5 or FEC 8 task, SSI, L/HIRF, stand-alone EWISSafety-related: the competent authority evaluates the data and approves the AMP revision directly.
FEC 6, 7 or 9 task, zonal taskNon-safety-related: indirect approval through the CAMO procedure is possible, as described in FAQ 19061.

Two further links tie the FEC code to the AMP. Point M.A.302(g) requires a reliability programme when the AMP of a complex motor-powered aircraft is based on MSG logic or on condition monitoring, and that programme supplies the in-service evidence any escalation needs. And because MRB intervals assume a typical utilisation, Appendix I to AMC M.A.302 expects the AMP to state the anticipated utilisation with a tolerance of not more than 25%.

 

Worked Example (fictional data)

Engineering proposes escalating two tasks from 12 months to 18 months, both with three years of clean findings.

Task A: a check of a galley drain line heater, source 'MRB 7'. FEC 7 is economic, so the task is not safety-related. With an approved CAME procedure and the M.A.302(c) conditions met, indirect approval is possible.

Task B: an operational check of a standby hydraulic pump, source 'MRB 8'. FEC 8 is hidden safety, so the escalation is safety-related and needs direct approval by the competent authority, supported by the reliability data.

Same interval, same findings, two different routes. The FEC code made the difference.

Five mistakes we see in AMP work

  1. Treating the MPD as the AMP. The MPD is a source. The AMP is the operator's controlled document, adapted to configuration, utilisation and operation.
  2. Ignoring the source column. 'MRB 8' and 'MRB 7' look alike in a task list, but they follow different approval routes.
  3. Letting the MRB code hide a mandatory one. If a CMR or ALS reference sits beside the MRB code, the task is mandatory.
  4. Escalating on silence. Zero findings on a handful of results is not evidence. Escalation needs task-level data from a reliability programme or in-service analysis (FAQ 48248).
  5. Confusing escalation with a permitted variation. An escalation is a permanent AMP change. A permitted variation is a one-off extension for one aircraft on one occasion.

 

Learn to apply it on a real AMP

Reading an MPD line correctly, routing a change and defending an interval in front of an inspector are skills, and skills need practice. Our three-day, live online EASA Aircraft Maintenance Programme (AMP) Development course works through M.A.302, MPD and ALS sources, FEC-based change routing, intervals and reliability data, with four practical exercises built on a fictional fleet. Exercise 1 is an MPD extract classification in which you decode source codes and FEC categories line by line.

 

For the regulatory side of the programme itself, see our guide to EASA AMP Requirements and M.A.302 Compliance and our article on instructions for continued airworthiness under 21.A.7

 

References

  • Regulation (EU) No 1321/2014, Annex I (Part-M), point M.A.302 and Appendix I to AMC M.A.302.
  • Regulation (EU) No 748/2012, Annex I (Part 21), points 21.A.7 and 21.A.31.
  • EASA Certification Memorandum CM-MRB-001, Maintenance Review Board Report / Maintenance Type Board Report Development Process.
  • EASA procedure PR.CSERV.00003, Maintenance Review Board.
  • EASA FAQ 48248 (escalation of AMP task intervals) and FAQ 19061 (indirect approval of the AMP).
  • EASA CS-25, AMC 25.19 (certification maintenance requirements); AMC 20-21 (EWIS maintenance, EZAP).
  • International Maintenance Review Board Policy Board (IMRBPB) issue papers, published on the EASA website.
  • A4A, MSG-3: Operator/Manufacturer Scheduled Maintenance Development, Volume 1 (Fixed Wing Aircraft).

 

Disclaimer

This article is for general information and training. It is not approved maintenance data. Rules, AMC, FAQs and MSG-3 revisions change; check the current official texts before applying them.

 

Frequently asked questions

What is MSG-3 in aviation maintenance?

MSG-3 is an industry decision logic, published by Airlines for America (A4A), used to develop the initial minimum scheduled maintenance for new aircraft and engines. It works top-down from the consequence of each functional failure and selects a task only if it is applicable and effective.

What is an MRB report (MRBR)?

The MRB report contains the initial minimum recommended scheduled maintenance and inspection requirements for an aircraft type. Industry working groups produce it with MSG-3 logic, and the authority, EASA in Europe, approves it through the Maintenance Review Board process.

What do FEC codes 5, 6, 7, 8 and 9 mean?

They are the MSG-3 failure effect categories for systems and powerplant: FEC 5 evident safety, FEC 6 evident operational, FEC 7 evident economic, FEC 8 hidden safety and FEC 9 hidden non-safety.

What is the difference between FEC 5 and FEC 8?

Both are safety categories. An FEC 5 failure is evident to the crew and directly affects operating safety. An FEC 8 failure is hidden, and affects safety only in combination with one additional failure, so its tasks are often failure-finding checks.

Who approves the MRB report in Europe?

EASA approves the MRB report. An EASA MRB chairperson leads the review team and recommends approval, and the approval letter is sent to the applicant, as described in EASA Certification Memorandum CM-MRB-001.

Is the MPD the same as the aircraft maintenance programme?

No. The MPD is the type certificate holder's planning document, containing MRB tasks and other sources. The AMP is the owner's or CAMO's own controlled document under M.A.302, adapted to the aircraft's configuration, utilisation and operation.

Can a CAMO escalate an FEC 8 task by indirect approval?

No. EASA FAQ 48248 treats FEC 5 and FEC 8 tasks as safety-related. Escalating them needs direct approval of the AMP revision by the competent authority, supported by reliability or in-service data.

Which MRB tasks does EASA treat as safety-related?

Where the type went through the MRB process, EASA FAQ 48248 lists FEC 5 and FEC 8 systems and powerplant tasks, structural significant item (SSI) tasks, L/HIRF tasks and stand-alone EWIS tasks from the EZAP.

Are CMRs part of the MRB report?

No. Certification maintenance requirements are set during type certification to detect latent failures (AMC 25.19) and are mandatory. The MRB analysis may produce a similar task, but where a CMR code appears the mandatory requirement governs.

When does an AMP need a reliability programme?

Under M.A.302(g), the AMP of a complex motor-powered aircraft must include a reliability programme when it is based on maintenance steering group logic or on condition monitoring.

Which MSG-3 revision applies to a new aircraft type?

EASA CM-MRB-001 expects the applicant to use the latest MSG-3 revision published at the date of the type certificate or supplemental type certificate application. Check the MRB report for the revision actually used.

Where can I learn to apply MSG-3 and FEC codes to an AMP?

AviaThrust's three-day, live online EASA AMP Development Course (AT-0026-00) covers M.A.302, MPD and ALS sources, FEC-based change routing, intervals and reliability, with four practical exercises.

Related reading and training

EASA aircraft maintenance programme (AMP) development course for CAMO engineers
Training Course
EASA Aircraft Maintenance Programme (AMP) Development Course

Three days, live online: read MPD lines and FEC codes, route AMP changes for direct or indirect approval, set intervals and use reliability data. Four practical exercises.

View Course
EASA AMP requirements and M.A.302 compliance guide for CAMOs
EASA AMP Requirements and M.A.302 Compliance

What the AMP must contain, how it is approved and how it is kept current.

Read Article
EASA instructions for continued airworthiness (ICA) under 21.A.7
Instructions for Continued Airworthiness (ICA) under 21.A.7

How CAMOs and Part-145 organisations identify, control and use ICA.

Read Article

Our Services